Project Slipway

Work on the new slipway and landing stages in full swing.

Sudbury Rowing Club working with Gunite Solutions Ltd

  • 108 tons of concrete & soil taken out 6 tons of general waste taken out
  • 45 tons of type 1 hardcore put down
  • 98 tons of RC 35/40 concrete put down – every bit reinforced with steel
  • 300 linear meters of shuttering
  • 80 meters of fibreboard
Day 1 – Monday 21st August
Day 1 – Monday 21st August
Day 2
Day 2
Day 3
Day 3
Day 4
Day 4
Day 5 – Friday 25th August
Day 5 – Friday 25th August
Day 6 – Tuesday 29th August
Day 6 – Tuesday 29th August
Day 7
Day 7
Day 8
Day 8
Day 9
Day 9
Day 9/10 – Saturday 2nd September
Day 9/10 – Saturday 2nd September
The finishing touches...4th-19th September!
The finishing touches...4th-19th September!
Before and after
Before and after
Before and after
Before and after
Before and after
Before and after
Before and after
Before and after
Before and after
Before and after
Before and after
Before and after
Before and after
Before and after
Our brand new sparkly slipway
Our brand new sparkly slipway
Published